Best of intentions reduced to dust in Sutherland Press building demolition


city_scope_logo-cmykCity manager Wendell Graves advises Schouten Excavating employees are expected on site at the Sutherland Press building the week of Oct. 16 to begin demolition work.
According to the city’s agreement, the contractor has 30 days to demolish the four-storey structure, although as chief building inspector Chris Peck indicated previously, the site itself may not be totally cleared of debris in that period of time.
Once demolition has reached a certain stage, re-opening of the adjacent transit centre will be possible.
At this point, Talbot Street will remain open during the demolition and Graves adds Moore Street may be opened to traffic sooner than expected if the demolition work can be contained on site. Continue reading

Advertisements

Only a matter of time now for Sutherland Press building


Will it be a case of third-time success for the City of St. Thomas? Monday evening (Sept. 18), city council accepted the $197,000 tender from Schouten Excavating of Watford to demolish the derelict Sutherland Press building that looms over the downtown core.
Schouten had been the successful bidder in 2016 when it was awarded the contract for $101,000.
It’s the third time in nearly a decade the city has attempted to level the building that dates back to 1913. Continue reading

Third time lucky as city pursues demolition in Sutherland saga?


Round 3 of the Sutherland Press demolition derby is officially underway. At Monday’s council meeting, city manager Wendell Graves advised the paperwork is being drawn up this week seeking requests for proposal for demolition of the four-storey Sutherland Press building.
It’s the third time in nine years the city has undertaken this process, and the fact the building that dates back to 1913 is still standing is testament to the success of the previous two attempts.

SUTHERLAND BLDG full

Sutherland Press building in 2008, prior to partial demolition of front face

In 2008, a determination from Justice David Little paved the way to for partial demolition of the top floor of the structure. A process halted almost immediately by Justice Peter Hockin. The same Justice Hockin who, in June of this year, upheld the validity of a pair of work orders issued by the city calling for remedial work to be performed on the structure.
In other words, Hockin concurred with engineering reports undertaken by the city and ruled the building is unsafe.
And that has prompted a third kick at the demolition can.
In between these two attempts, the city in February of 2016 awarded a demolition tender to Schouten Excavating of Watford in the amount of $101,135.
Earlier this month, Graves confirmed  “technically that tender was not active.”
And so, here we go again as the city takes a cautious approach to proceeding with demolition of the building owned by David McGee of Toronto.
Speaking with Graves in his office today (Aug. 22), he made it clear everything must be buttoned down when announcing the winning bid because McGee ultimately will be presented with the bill.

sutherland conceptualjpg

A conceptual drawing of what the Sutherland Press building might possibly look like if successfully converted into a condominium development.

Will companies be reluctant to submit proposals because of past history?
Graves felt this would not be a problem as there was no shortage of interested parties in 2016.
He added a report should come to council in mid-September with the tender proposals.
Meantime,McGee’s lawyer Valerie M’Garry was unavailable today for comment.
Following Hockin’s ruling in June, she told City Scope “We’re optimistic of approaching the municipality and saying here’s a proposal for you, let’s move forward rather than spending time on appeals and things like that.”
She added at that time,  “I think there’s an onus on both parties. We have to pony up and they have to be willing to listen. Both parties have to be willing to come to the dance. And we can do some things that will assuage the city’s concerns and ultimately be to the advantage of the building.”
Graves confirmed again today, neither M’Garry nor McGee has engaged in any dialogue with the city on the next step following the ruling from Justice Hockin.

Related posts:

Charting the pathway to demolition and freedom for the hostages

No throwing caution to the wind in this chapter of the Sutherland Saga

After nine years, it’s time to pony up and listen

Thirty days and counting in the Sutherland Saga

Questions and comments may be emailed to: City Scope
Visit us on Facebook
city_scope_logo-cmyk

Charting the pathway to demolition and freedom for the hostages


city_scope_logo-cmykAfter nine years, the city finally benefits from a legal determination the Sutherland Press building is, indeed, unsafe but does the ruling from Justice Peter Hockin mean the hostage taking in St. Thomas is nearing a conclusion?
The city has chosen to take a cautious approach, something it can’t be faulted on after a 2008 ruling from Justice David Little triggered partial demolition of the top floor of the four-storey structure. A process halted almost immediately by the same Justice Hockin.
What is most frustrating is the continued lack of movement on the part of owner David McGee since the June 28 decision that upheld a pair of city work orders. Attempts by McGee and his lawyer, Valerie M’Garry, to convince both Hockin and city staff that the financial picture had somehow improved – to the tune of $50,000 – were laughable. 
Surely the unpaid bills would gobble that up in prompt fashion.
M’Garry had indicated to this corner the next step would be dialogue with the city on moving forward.
So, how is that working out?

Continue reading

It’s time to move on, the hostages are beyond the restless stage


city_scope_logo-cmykLaying down the law in the Sutherland Saga originated from an unlikely source this week in the form of Ontario Superior Court Justice Peter Hockin, one of the original cast members in the near-decade long run of this soap opera.
Tuesday at the Elgin County Courthouse, Hockin was set to preside over the hearing involving the City of St. Thomas versus Sutherland Lofts owner David McGee.
McGee, through lawyer Valerie M’Garry, is challenging an unsafe building order issued Oct. 28 by the city that gave him until Dec. 15 of last year to provide a detailed work plan and schedule repairs to begin early last month on the four-storey structure.
But, as was the case on Jan. 3, the hearing was a non-starter due to M’Garry’s ill health.

Continue reading