Councillors are willing to do ‘a circus performance’ for childcare facility; the mayor would rather deflect


city_scope_logo-cmykCouncillors sent a clear message to Mayor Joe Preston and city manager Wendell Graves this past Monday.
Push forward with the construction of an 88-space downtown childcare centre in an expedient fashion.
Preston responded as he has in the past, by deflecting.
In his report to council, Graves recommended retendering the project this fall with construction to be completed by the end of next year.
The reason for the delay in going out to tender, advised Graves, is an increase in costs in the neighbourhood of $300,000 when the project was tendered last month.
Putting the cost estimate in the $4.3 million range whereas just over $4 million has been budgeted for the badly needed childcare facility to be located on St. Catharine Street.
“Childcare spaces in our community are desperately needed,” reminded Coun. Lori Baldwin-Sands, “and I believe once we start coming out of COVID a little more rapidly, the people who are going to be requiring the service of daycare is going to be growing exponentially.”

Continue reading